SK hynixHBM advanced packaging — Purdue Research ParkHero
$4.83B investment1,000 jobsH2 2028 timeline
Change: +$958M federal investment
Latest News
History — original announcement & expansions ›
- Announcement
- $3.87B · 1,000 jobs · production H2 2028
- Announced
- April 2024
- Apr 2024$3.87B announcedFirst HBM packaging anywhere in US; first SK hynix fab outside South Korea
- Aug 2024+$458M (CHIPS prelim)Plus $500M CHIPS Program Office loan
- Dec 2024→ $958M (CHIPS final)Confirmed at prelim level; ~25% federal cost-share
- Feb 2026$98M building permits filedFoundations: office, fab, central utility
- Mar 2026$1.21M permit (temporary power)Phase 1
- Apr 2026Foundation piling begins Apr 17; vertical construction expected H2 2026
Verify · Market is small: West Lafayette ~45K + Lafayette ~70K = ~120K MSA. The 7,000 total figure is SK hynix's own projection covering construction + suppliers + R&D + induced services across the full ramp — not net-new residents. Even the 1,000 direct number partially backfills Purdue grads who would have stayed locally anyway. Repricing window is the 2026–2028 construction wave (peak ~2,500–3,000 trades + ~200 Korean relocators) plus the 2028 production ramp; supply response (a 1,200-unit Millbrook project broke ground Apr 2026) likely catches demand by 2029. Single-catalyst risk is real — Purdue is anchor demand but already priced in.