MicronMemory fab campus — ID1 + ID2, south BoiseHero
$50B investment~17K jobsMid-2027 timeline
Change: +$35B investment
History — original announcement & expansions ›
- Announcement
- $15B · 2,000 jobs · production by 2025
- Announced
- September 2022
- Oct 2023+$2B (ID1 fit-out)Groundbreaking; first new leading-edge memory fab in US in 20 yrs
- Apr 2024+$6.14B (CHIPS prelim)Multi-state preliminary memo; Idaho ~$1.5B share
- Dec 2024→ $6.165B (CHIPS final)Final award confirmed at preliminary level (no Samsung-style cut)
- Jun 2025+$35B (ID2 added)Boise capex stepped up to $50B; ID2 production targeted before any NY fab
- Sep–Nov 2025Exyte general contractor terminated; 201 layoffs; replacement GC selected
- Dec 2025Record FQ earnings; ID1 first wafer pulled forward to mid-2027; Micron 'more than sold out'
- Apr 2026+238 acres (annexation)Painted Ridge expansion — 40-acre electrical yard, 12 transformers, 40-ft berms; community pushback on noise / fire / visual
Verify · Housing already moved on Micron speculation: Boise median ~$495K is 18% above national, +6% YoY through 2025. Premium Treasure Valley submarkets priced 2022–2023; today's entry is mid-wave, not pre-wave. The 17K ecosystem figure is direct + indirect + induced, not net direct adds — Micron has been Boise's largest private employer for decades, so some hiring backfills internal moves rather than landing new households. ID2 (Jun 2025) is the genuine new repricing fuel.